Description of the investment
Investment: JURRASIC SALMON
Location: DREŻEWO NEAR KARNICE
Start: I.2014
End: V.2015
Construction of a hall and economic and production buildings in an agro-fisheries livestock farm along with land development and external installations with a total area approx. 8,000 m2.
The hall includes: office and social rooms, laboratory, hatcheries, fish tank rooms, heat pump room, water treatment plant, biofilters, denitrification, freezers and cold stores as well as a storage section.
PE tanks were made:
13 items with a capacity 3,32m3
9 items with a capacity 16m3
6 items with a capacity 40m3
Reinforced concrete tanks were made:
4 pcs. o. 242 m3 (tank size: d = 7.85m, h = 6m)
3 pcs. o. 791 m3 (tank size: d = 14.2m, h = 6m)
3 pcs. o. 408m3 (tank dimension d = 10.2m, h = 6m)
4 items with a capacity 283m3 (tank dimension d = 8,5m, h = 6m)
A number of reinforced concrete chambers were made, the largest consisting of 17 chambers and placed at 6.5 m below the level of the floor.